1). Before installation, all components and connecting parts of the mixing equipment should be counted according to the packing list, and any damage to the equipment during transportation should be checked. If there is any damage or loss, it should be repaired and replenished.
2). Remove dust and debris from the equipment. The installation of this equipment requires one crane with a lifting capacity of 40 tons and a lifting height of 20 meters or more, as well as one 8-ton crane, 2-4 skilled lifting workers, and 3-5 auxiliary workers.
3). Before installation, a plan layout should be made according to the foundation drawing and site conditions, and then construction should be carried out according to the requirements of the foundation drawing. Ensure accurate relative position dimensions and calibrate the foundation plane with a level. The foundation of the host and cement silo should be constructed simultaneously. To ensure good grounding of the equipment, grounding electrodes should be pre embedded during construction, with a grounding resistance of less than 4Q
Apr 15, 2025
Leave a message
What are the preparations for the installation of a concrete mixing plant?
Send Inquiry