Precautions for the use of concrete mixing plant and daily maintenance

The matters needing attention in the operation of the concrete mixing plant are as follows:

   1. When the equipment is working, it is strictly forbidden to enter the material storage area and under the lifting bucket; it is strictly forbidden to put the limbs in the hopper and mixing barrel for exploration;

  2. When the dragline is stuck by an obstacle, it is not allowed to pull up forcibly or use the dragline to lift heavy objects, and no reverse operation is allowed during the pulling process;

  3. When the mixer is fully loaded, it must not be shut down. When there is a problem or power failure, the power supply should be cut off immediately, the switch box should be locked, the concrete in the mixing bucket should be cleaned, and the problem should be eliminated or waiting for a call;

  4. Do not work with overload, and check the working condition of the motor. When there is abnormal noise or the temperature rises, you should stop it immediately for checking.

How to do a daily inspection of the concrete batching plant?

 Before the concrete mixing station works, we need to do its daily inspection work. Then, what do we need to check? Let's take a look at it together:

   1. Check the working conditions of the lubrication points of each rotating part, and replenish the lubricating oil in time.

   2. Check the amount of lubricating oil in the lubricating oil cup of the mixer and replenish the lubricating oil in time.

   3. Check the oil level of the lubricator on the gas system once a week, and use lubricating oil with a viscosity of 2.5 to 70 E.

  4. Open the drain valve once a day to drain the condensed water in the air compressor and air storage tank.

   5. Fasteners (such as bolts and nuts) should be checked frequently for looseness. If any looseness is found, tighten them in time, especially for parts subject to variable amplitude load.

  6. Regularly check whether the equipment of the water supply, gas supply, and admixture system is normal.

   Seven. Check whether the electrical control system and various instruments are normal.

   8. Check whether the mixing shaft and barrel of the concrete mixing station mixer are clean and clean. If there is too much concrete condensed on the mixing shaft, manually clean it.

   Nine. Regularly clean or replace the filter in the dust collector of the powder tank.

  10. If the machine is down for more than a week, empty the materials (such as cement, water, admixtures, and various aggregates) in each measuring hopper, and clean the mixer, the discharge hopper, etc., to avoid material hardening.

   Note: When cleaning the filter in the dust collector of the powder tank, it cannot be washed with water, but can only be cleaned with air blowing or a soft brush.